Here are answers to the most common questions we receive. 
Don’t see the answer? Please get in touch below using the form below.

  • Estimated cost is $1,500,000
  • Design for a regulation 6 lane track with flat profile
  • Includes engineering fees and industry standard contingency fund
  • Price does not include GST as project is being built by a CRA Registered Charity
  • Estimate done on November 2nd, 2020, by Koers and Associates Engineering
  • The annual cost of maintenance and operation will be the same or less than existing maintenance 
  • Grounds maintained by School District 69 (Qualicum)
Community support has been received from:
  • City of Parksville
  • School District 69
  • Regional District of Nanaimo
  • Town of Qualicum Beach
  • Electoral Areas G and H
  • Parksville-Qualicum Beach Community Foundation
  • Lions Club
  • Mosaic Forest Management
  • Public donations
  • Business donations

An accessibility ramp is included in the budget.

  • Silent auction
  • Community Love Run
  • WestJet Raffle
  • Dance/Concert
  • Bottle Drives
  • No added lighting is budgeted at this time
  • There is existing parking at Ballenas Secondary and PASS/Woodwinds facilities

Public washrooms have not been budgeted at this time.